Kiosks

HPWOCE1042
Permit Description

For the installation of power for a kiosk into a City of Houston service panel. 

Admin fee: $134.28
Plan review fee: $96.67 per sheet(changes yearly)
Plan Review: Required
Inspection: Required
Renewal: Not Required
Valid Period: 1-Year
Processing Time: 8-10 Business Days
Houston Public Works

1002 Washington Ave., 2nd floor

Houston, TX. 77002

8:00 am to 3:30 pm
What You Need
  • Provide a method of payment.
  • Engineering Firm in good standing with the Texas Board of Professional Engineers.
  • Plan sets must comply with the guidelines set by the City of Houston Infrastructure and Design Manual. 
Apply Online
  1. Create an account for or log into iPermits Portal.  
  2. Complete the "Office of the City Engineer Plan Review Application."
  3. Complete payment of plan review fee (credit card or e-check).  
  4. Follow the invitation email to upload plans to ProjectDox and complete your task. 
Conditions & Exceptions

The approved plans are only valid for one year. 

Inspection
What You Need
  1. After issuing the approved permit, the customer is required to give a 48-hour notice to the inspector's group prior to starting any paving construction work.
    • Note: The inspector's group contact information can be found on the cover of the approved plans.  
  2. Additional permits will need to be pulled based on project scopes, such as mobility permits or street cut excavation permits.