Pipeline Permit (Oil & Gas)

HPWOCE1004
Permit Description

In 2001, the City of Houston passed Ordinance No. 01-1078 so that no person or company may own, maintain, operate, acquire, construct, or extend a pipeline for the transportation or distribution of natural gas or liquids in a City street without a permit.

Pipeline companies are required to submit mapping information and obtain a permit ordinance. Once all documents and fees are received, Houston Public Works initiates the permitting process through to City Council for approval.

After Approval

Notify the City Engineer's Construction Services inspectors 48 hours prior to commencing work.

Fee: $2,685.61 (see Conditions & Exceptions)
Admin fee: $33.56
Renewal fee: $1,342.81 (see Conditions & Exceptions)
Plan Review: Required
Inspection: Not Required
Renewal: Required
Valid Period: 30 years
Processing Time: 120 days
What You Need
  • Pipeline Application Form 
  • Application Fee
  • Questionnaire
  • Certificate of Insurance
  • City Approved Drawing # (new application only)
  • GIS Mapping Data
Apply in Person
  1. Submit completed application and supporting documents in person to Pipeline Permit Section located at 1002 Washington Ave. 2nd Floor.
  2. Complete payment of application fee at the cashier station located on the 1st floor (cash, check, debit/credit card).
Apply by Mail

Mail the completed application, supporting documents and payment (certified or cashier's check only) to:

City of Houston Pipeline Permits Section
1002 Washington Ave., 2nd Floor
Houston, TX 77002

Plan Review
What You Need

Submit Plan & Profile

Submit Plans in Person

Submit plans in person to Pipeline Permits Section, located at 1002 Washington Ave. 2nd Floor.

Renew
What You Need

Renewals are due January 1 of each year. Invoices are sent via email 60-90 days prior to expiration. Annual payment amount and invoice.

Renew in Person

Bring the invoice and a form or payment to Pipeline Permits Section located at 1002 Washington Ave. 2nd Floor. Payment is accepted at the cashier station located on the first floor (cash, check, debit/credit card).

Renew by Mail

Mail the invoice and payment (check only) to:

Pipeline Permits Section
1002 Washington Ave., 2nd Floor
Houston, TX 77002