Private Service Connection Fee

Instrument Reference Number
HPWUA1029
Areas of Interest
Valid Period
15 years
Inspection
Required
Renewal
Not Required
Plan Review
Required
Processing Time
2 months
About

Sets a motion to partially reimburse developers who build pipe from other developers connecting to that pipe.

After Approval

When other developers connect to that pipe, payments are gathered and paid to the initial developer every May and November.

Conditions and Exceptions

Application must be within 90 days of project acceptance by Office of the City Engineer.

Apply What you need
  • Contracts with contractor, engineer and testing agency 
  • Acceptance documents from the Office of the City Engineer
  • Disinfection documents from Houston Water for water pipe 
  • Proof of payment - all invoices and canceled checks or wiring documentation
Apply in Person Steps

Set up meeting with Utility Analysis Developer Services; Call 832.394.8998 or 832.394.9001.

Apply Conditions & Exceptions

Must be within 90 days of pipe acceptance by Office of the City Engineer.


Source URL: https://www.houstonpermittingcenter.org/hpwua1029