Wastewater Capacity Reservation Name Transfer

Instrument Reference Number
HPWUA1007
Areas of Interest
Valid Period
Once transferred valid until wastewater capacity is used.
Inspection
Not Required
Renewal
Not Required
Plan Review
Not Required
Fee
$13.42
Admin fee
$5.00
Processing Time
12 business days
About

If impact fees were paid but development never occurred, the capacity may be transferred from one property owner to the new owner of the same site through a Name Transfer Application. 

After Approval

Upon completion of the transfer, a new Wastewater Capacity Application will be needed to be submitted

Apply What you need

All name transfer applications must be notarized and signed by both the previous and current property owners and accompanied with:

  • Proof of ownership: a recorded deed, title report, title option or title insurance policy for the property.
  • Copy of the Wastewater Capacity Reservation (WCR) Letter
  • Impact Fee or Capital Recovery Charge Receipts
  • Site plan of the land under consideration
  • Processing fee in the form of a check or money order (Make payable to the City of Houston).
Apply Online Steps
  1. Email the completed application and supporting documents to: [email protected]
  2. Questions: reach out to an Assistant Project Manager or Supervisor via email or phone:

Source URL: https://www.houstonpermittingcenter.org/hpwua1007