Modular home (residence) Placement Permit

Instrument Reference Number
HPWCODE1126
Valid Period
6 Months
Inspection
Required
Renewal
Not Required
Plan Review
Required
Fee
See City of Houston fee schedule
Admin fee
$33.56
Plan review fee
See City of Houston fee schedule
Processing Time
15 Business Days
About

Construction of a new foundation and placement of a State of Texas approved modular home on a single family property.

After Approval

Permit must be kept on site until final approval is granted.

Apply What you need
  • Building Permit Application
  • Declaration in Support of Application for City of Houston Building Permit
  • Complete Set of Plans Uploaded
Apply Online Steps

1. Log in or create an iPermits account at: https://www.hpceservices.org/

2. Complete building permit application

3. Pay plan review fee(s)

4. Receive email invitation to upload plans.

Apply Conditions & Exceptions

Requires approval by structural, utilities, and planning. Certain conditions may trigger a required review by the stormwater, traffic and / or floodplain groups.

Plan Review What you need

Building Permit Application and Complete Set of Plans Uploaded.

Plan Review Submit Online Steps

Once application is approved and the plan review fee (PX) has been paid, an email to upload and submit plans will be sent to the applicant.

Plan Review Conditions & Exceptions

Plans provided for the structure (other than the foundation) must have the State of Texas approval seals.

Inspection What you need

Approved plans must be on site for inspection.

Inspection Schedule by Phone Steps

To schedule inspections, contact the Interactive Voice Response (IVR) System at 713-222-9922. Trade inspections must be scheduled by the appropriate registered licensed contractor.

Inspection Schedule Online Steps

Enter the appropriate project number into the field and click Submit button.


Source URL: https://www.houstonpermittingcenter.org/hpwcode1126