Paving Permit (Right of Way)

HPWOCE1034
Plan Review
Not Required
Inspection
Required
Renewal
Not Required
Fee
$87.24
Admin fee
$32.16
Valid Period
1 year
Processing Time
2-3 business days

About

Paving permit is granted for constructing/paving public street inside City limits. For the repair, improvement and/or maintenance of an alley

After Approval

After permit is issued, all paperwork will be delivered to Construction/Inspection group, customer is required to call the inspector on file 48 hours before construction starts.

Conditions & Exceptions

Requires Plan Review for Utilities in the Right of Way prior to applying for permit. The approved plans is only valid for one year.

Statutory Authority
What You Need

1. Two copies of approved Plan & Profile drawings; 2. Three copies of original application form; 3. Original bond.

Apply Online

Email: [email protected]

Apply in Person

1. Bring the completed application and required documents to the 2nd floor. 2. Bring the sales order to the Cashier Booth on the first floor to complete payment for the plan review fee. 3. Bring the payment receipt to the Intake Window on the 2nd floor. Permit will be issued.

Conditions & Exceptions

the approved plans is only valid for one year