Plan Review
Required
Inspection
Required
Renewal
Not Required
Admin fee
$118.91
Plan review fee
$85.61 (per plan sheet)
Valid Period
1 year
Processing Time
3-4 days

About

For the construction of on-street parking (parking pad)

After Approval

Permit must be kept on premises in public view. Scheduled inspections are conducted.

Conditions & Exceptions

Inspection is required after permit is issued

What You Need

A method of payment.Engineering Firm in good standing with the Texas Board of Professional Engineers. Two sets of plans. Plan sets must be in compliance with guidelines set by the City of Houston Infrastructure and Design Manual.

Apply in Person

1. Bring the completed plan review application and required number of sets depending on the projects location to the Intake Window located on the 2nd floor. 2. Bring the sales order to the Cashier Booth on the first floor to complete payment for the plan review fee. 3. Bring the payment receipt to the Intake Window on the 2nd floor. Plans will be routed to the appropriate disciplines.

What You Need

Once construction is completed, client will notify Construction Services Section for inspection.

Schedule by Phone

Contact the assigned inspector provided on the receipt or permit to schedule an inspection.